Angamaly–Sabari Rail Line

Sanctioned in 1997-98 to connect Angamaly with Erumeli/Sabarimala. Only about 7 km near Kalady was built before work stalled over land acquisition and cost sharing. Kerala has repeatedly offered a 50% cost share to revive it.

Sanction year
1997
Sanctioned cost
₹3,800.94 cr
Route length
111 km
Railway division
Thiruvananthapuram

Timeline

  1. 1 Feb 2024Sanctioned

    Revised cost estimate placed at about Rs 3,800 crore; work remains suspended pending a cost-sharing agreement.

    Source
  2. 1 Mar 2021Sanctioned

    Kerala government conveys willingness to share 50% of the project cost; Railway Board seeks a formal commitment.

    Source
  3. 1 Apr 1997Sanctioned

    Project sanctioned in the 1997-98 railway budget.

    Source